Solution 1

There currently is no "direct" or "free" way to chain triggers with Quartz. However there are several ways you can accomplish it without much effort. Below is an outline of a couple approaches:

One way is to use a listener (i.e. a TriggerListener, JobListener or SchedulerListener) that can notice the completion of a job/trigger and then immediately schedule a new trigger to fire. This approach can get a bit involved, since you'll have to inform the listener which job follows which - and you may need to worry about persistence of this information.

Another way is to build a Job that contains within its JobDataMap the name of the next job to fire, and as the job completes (the last step in its Execute() method) have the job schedule the next job. Several people are doing this and have had good luck. Most have made a base (abstract) class that is a Job that knows how to get the job name and group out of the JobDataMap using special keys (constants) and contains code to schedule the identified job. Then they simply make extensions of this class that included the additional work the job should do.

Ref: http://www.quartz-scheduler.net/documentation/faq.html#how-do-i-chain-job-execution?-or,-how-do-i-create-a-workflow?

Solution 2

I know this is an old question, but nevertheless there are 2 more options available to chain the execution of your jobs which people can find useful:

1) Use the JobChainingJobListener that is included in the standard Quartz distribution since very early releases. This listener allows you to programmatically define simple job chains using its addJobChainLink method.

2) Use a commercial solution such as QuartzDesk that I am the principal developer of. QuartzDesk contains a robust job chaining engine that allows you to externalize the definition of your job chains from the application code and enables you to update your job chains at runtime through a GUI without modifying, redeploying and restarting your application. A job chain can be associated with a particular job, trigger or it can be a global job chain that is executed whenever any of your jobs execute (useful for global job execution failure handlers etc.).

QuartzDesk GUI: Editing a job chain target

Share:
18,598
Sanchit
Author by

Sanchit

I'm a web developer working on Java, Databases, Salesforce, Webservices and jQuery.

Updated on June 15, 2022

Comments

  • Sanchit
    Sanchit about 2 years

    I'm making use of Quartz Scheduling and there are 2 jobs. First Job is performing the tasks for around 2 minutes and the Second one is to be setup for Cleaning Operations of Temporary Files. So, I need to setup the Schedule to work in a way that after the first job is executed/finished performing tasks I need to do the cleaning operations with the help of Second Job.
    Considering the Example 9 - Job Listeners under Quartz 2.1.x which states that we can define a method named jobWasExecuted( _, _ ); in the Job Listener and it executes when the 1st job is executed/or comes in running state.
    Are we able to setup the schedule which can listen for the first job finishing then executes second? or,
    Are we able to define the join() method like in Java Multithreading which can execute on the completion of first job?

  • Sanchit
    Sanchit over 11 years
    Thanks Vishal the chaining of jobs seems to be what I need.